Abstract. Battery testing
for photovoltaic (PV) applications is funded at Sandia under the
Department of Energy's (DOE) Photovoltaic Balance of Systems (BOS)
Program. The goal of the PV BOS program is to improve PV system
component design, operation, reliability, and to reduce overall
life-cycle costs. The Sandia battery testing program consists
of: 1) PV battery and charge controller market survey, 2) battery
performance and life-cycle testing, 3) PV charge controller development,
and 4) system field testing. Test results from this work have
identified market size and trends, PV battery test procedures,
application guidelines, and needed hardware improvements.
The Photovoltaic (PV) battery testing work at Sandia is funded by the Department of Energy's (DOE) Photovoltaic Balance of Systems (BOS) Program. Additional funding for the PV battery market survey has been provided by Sandia's Battery Analysis & Evaluation Department funded by the DOE Office of Utility Technology. In addition to work conducted at Sandia, the Florida Solar Energy Center (FSEC) is also funded by Sandia to conduct PV battery cycle-life testing and field evaluations. The PV battery testing at Sandia includes:
The goal of this work is to improve PV system component design,
operation, and reliability to reduce overall PV system life-cycle
costs.
Batteries in PV systems are subject to performance losses that
stem from five basic sources: 1) limited time and energy available
to recharge the battery, 2) hardware failure, 3) inadequate battery
maintenance, 3) improper system design, and 4) improper battery
design. This report only focuses on PV battery charging issues.
Battery recharge in stand-alone PV systems is subject to solar
resource that can be well below normal for weeks at a time resulting
in a battery that is consistently under charged. The PV system
battery recharge methodology is known in the battery industry
as "opportunity charging". "Opportunity charging"
differs greatly from traditional battery applications such as
motive power deep-cycle, starting lighting and ignition (SLI),
or uninterruptible power supply (UPS) float applications in that
when the battery is under charge it may only receive a partial
incomplete charge for long periods of time. This partial charge
condition causes electrolyte stratification and/or irreversible
sulfation in flooded deep-cycle lead-antimony batteries. After
months in a partial charge condition, full recovery generally
requires more charge than most PV/charge controller systems are
capable of providing.1 The degree to which premature
PV battery capacity loss occurs in PV systems with flooded batteries
is dependent on system design, regulation voltage, and battery
design. Even well designed PV systems experience some premature
battery capacity loss because of the lower PV regulation voltages
and the lack of battery equalization.2
In addition to the problems associated with flooded batteries,
the new gel or absorbed glass mat (AGM) valve regulated lead-acid
(VRLA) batteries have additional PV battery charging difficulties.
This is due primarily to the fact that VRLA batteries require
a more precise charge control algorithm which varies depending
on the manufacturer and type of VRLA battery. PV systems will
typically use very simple on/off charge controllers with low reconnect
voltages (~13.4 volts). The main problem is that these simple
on/off charge controllers can be very inefficient because they
tend to terminate charging prematurely. VRLA batteries are much
more sensitive to regulation voltage (typical 14.1 to 14.4 volts
at 25C) and require much more time at the regulation voltage than
flooded batteries. They are also much less tolerant of excess
charge. VRLA battery manufacturers recommend constant voltage
charging for their batteries, but most PV systems use on/off charge
control.3 The result is an under- or over-charged
VRLA battery. If the VRLA battery is being charged at an excessively
high voltage, then it will vent excess gas and lose capacity from
loss of electrolyte or battery dry-out. Permanent capacity loss
can also occur from under charging resulting in irreversible sulfation.4
There is just a narrow window of charging parameters that a VRLA
battery will operate under and still achieve rated cycle-life.
Most PV charge controllers are not designed for the more rigorous
requirements of a VRLA battery.
Present PV systems using batteries for backup power add at least
$0.10 to $0.50 per kWh to the system life-cycle cost (assuming
100% charge efficiency and full rated life of the battery).5,6
These battery cost values vary due to the quality and type of
battery used (golf cart vs. industrial VRLA). If true battery
charging efficiencies are factored (~70 to 90%) and battery life
is cut in half, then battery costs can easily exceed $0.26 to
$1.30 per kWh over the life of the system. This simple calculation
indicates that battery costs can be equal to or greater than the
life-cycle costs of the PV modules (assuming PV life-cycle costs
of $0.25 per kWh or ~$6/Wp). Therefore the potential cost benefit
to stand-alone PV systems is substantial if batteries meet their
rated life expectancy.
This survey was funded by the DOE Office of Utility Technology through Sandia's Battery Analysis and Evaluation Department in support of the Photovoltaic System Applications Department. The survey was conducted by Bob Hammond of Arizona State University to better define the market size, hardware, operating environments, and future growth trends. Survey participants included:
In addition to the survey, all participants were asked what they
felt Sandia could do to expand the market for PV batteries. The
completed results will be published by Sandia in December of 1996.
3
Table 1 presents a preview from the battery survey listing total
flooded and VRLA battery sales from the 21 PV system integrators
for 1995. The data from the system integrators indicates that
64% of the PV batteries sold by them are VRLA with a dollar value
of $3.4 million. A top-down market analysis, conducted by Bob
Hammond using data from national PV sales and the survey, projects
that the total US PV battery market should be about $34.7 million.
Therefore the above PV systems houses share of this market is
about 14%. The survey indicated that the majority of systems
installed by the above integrators are using VRLA batteries, and
with this in mind, it is very important to better understand the
charging requirements of these batteries in PV systems.
Table 1.
Total PV Battery Market For Surveyed
System Integrators

Included in the survey was a question directed to the PV charge
controller manufacturers and system integrators requesting input
on what Sandia could do to expand the PV battery market. The
most predominant response was to provide assistance in the characterization
of batteries for PV systems. Fifty-four percent of the small
system integrators and 71% of the large system integrators indicated
that this was their highest priority for support from Sandia.
Battery manufacturers over the years have directed their design efforts toward 1) automotive starting, lighting, and ignition (SLI) batteries, 2) uninterruptible power supply (UPS) batteries, and 3) deep-cycle motive power batteries. All of these applications have very specific use requirements that may or may not be appropriate for PV systems. Much of the SLI and motive power battery performance data is obtained using Battery Council International (BCI) test procedures.7 The BCI test procedures include specific tests for:
None of the above tests are specific to PV systems and the data
that is generated is not directly applicable to PV systems. Controlled
PV battery tests are not possible in fielded PV systems because
of variations in solar resource, therefore, an automated battery
tester was purchased from Firing Circuits to conduct PV battery
testing at Sandia. The indoor test data can be used as a basis
to modify system design, justify improved charge controllers,
and evaluate new battery charging strategies. Improvements in
PV battery performance will require a comprehensive approach that
includes laboratory testing, improved system designs, improved
battery application notes, improved charge controllers, and field
verification. This is the approach taken at Sandia's PV System
Applications Department.
Test results from previous indoor testing, using a 10% depth of discharge (DOD), identified several important points that need to be considered in any PV battery test procedure.8,9 The test procedure considerations are:
An example of the effect of charge rate on charge acceptance is
in Figure 1. Figure 1 shows a GNB VRLA battery's overcharge (Ah
charged - Ah load/Ah load x 100) as a function of the charge/discharge
rate and the number of consecutive shallow cycles. The DOD and
available Ah for recharge were the same for all test cases. As
seen in Figure 1, the percentage overcharge with this test procedure
is much higher (20 to 40%) for a 10-hour recharge and 8-hour discharge
than for a 5-hour recharge and 2-hour discharge (5 to 12%). GNB
recommends 5 to 10% overcharge for this 12-5000X VRLA battery.
Also shown in Figure 1 is the effect of shallow cycling, which
decreased overcharge or charge acceptance after each consecutive
cycle. Figure 1 indicates that variations in battery charge acceptance
will occur in PV systems because of changes in charge and discharge
rates.

Figure 1.
GNB 12-5000X Battery % Overcharge (Charge Acceptance) As Function
of Charge/Discharge Rate And Cycle Number
In order to optimize battery performance in PV systems the effects
of regulation voltage (Vr) set-points, charge/discharge rates,
and array to load ratios must be well understood. It is also
not known how the interaction of the above PV system parameters
affect battery cycle-life. Higher battery cycle-life in PV systems
is the end objective of the Sandia PV battery testing.
The most effective way to identify the effects and interactions
of the Vr set-point, charge/discharge rate, and array to load
ratio on battery cycle-life is the use of an experimental design
and statistical analysis technique called Design of Experiments.10
This technique will improve the quality of data, minimize testing,
and identify the interactive relationships between the variables.
In this case, the Design of Experiments procedure centers around
a statistical analysis software package called MINITAB® that
identifies the experimental design and processes the test results.
The experimental model used for this evaluation is called the
Central Composite Design and requires 20 test cases for three
variables. MINITAB® is capable of designing the test plan
and processing the cycle-life performance results to provide statistical
diagnostics, main effects plots, and performance contour plots
of all variables. This experimental technique is now being used
at FSEC to provide a comprehensive cycle-life performance map
of the GNB 12-5000X AGM VRLA battery which is very similar to
the GNB Absolyte IIP battery. Both batteries are commonly used
in PV systems.
The experimental design requires the identification of a low and
a high value for regulation voltage, charge rate, and C:L ratio.
The Design of Experiments software will identify the other points
required for the Central Composite Design (see Table 2).
Table 2. Test
Points For The 80 Ah GNB 12-5000X AGM VRLA Battery Test At FSEC
| Voltage Set-Point | |||||
| Charge/Discharge Rate (amps) | |||||
| Charge to Load Ratio (Based On Time) | |||||
| Temperature (Deg. C) | |||||
| Depth of Discharge (%) | |||||

Figure 2. Simulated Example: PV Battery Cycle-Life Test Sequence
The Central Composite Design provides a higher quality prediction
over the region of interest where main, interaction, and curvature
effects are needed. All three of the above effects are used by
MINITAB® to define the individual variable responses (Vr,
rate, C:L), and identify the regression equations and coefficients
necessary to map the response curvature which illustrates how
factors influence the performance response (cycle-life). For
this experimental design, MINITAB® has defined 20 tests for
the given variables in Table 1. There are 8 tests to measure
the response variable (Cycle-Life) at the corner (high and low)
points, 6 tests to measure the response variable at the axial
points (points on the axis outside the base cube), and 6 tests
to measure the response variable at the center point. The high
and low values are defined by the experimenter and MINITAB®
calculates the other levels. The completed test sequence provides
MINITAB® with all of the performance responses that are required
to obtain the Residual Model Diagnostics (Figure 3 ), Main Effects
Plot (Figure 4), and Performance Contour Plots (Figure 5). Three
contour plots are required to fully map the interactions of the
variables to the performance parameter (Cycle-Life).

Figure 3. Simulated
Residual Model Diagnostics

Figure 4. Simulated
Main Effects Plot

Figure 5. Simulated
Contour Plot Of Cycle-Life (CycLife) Vs. Regulation Voltage
(Vr) and Charge/Discharge Rate (CapRate)
Figure 6 and 7 show the preliminary battery overcharges and end
of discharge voltages from test case #1 and #15. This test sequence
is only being conducted using constant voltage charge control.
At a later time the pulse width modulated charge control algorithm
will be tested using a PV charge controller. In Figure 6, test
case #1 (corner point), the battery is not recharging all of the
deficit Ah. This is clearly indicated by the fact that in the
first three cycles, the recharge Ah are between 97 to 100% and
the EODV is dropping from 12.30 to 12.12 volts. It is interesting
to note that after the first three cycles, the battery begins
to receive a slight excess in recharge Ah (+2%). This is an indication
of an initial capacity loss and improved charge acceptance at
the lower battery capacity. The battery reached the abort criteria
soon after this chart was prepared (-20% Capacity Loss).
In Figure 7, test case #15 (center point), the battery recharge
Ah which are between 107 and 112% of the discharge Ah show that
the battery is receiving about 8% overcharge after the initial
25 cycles. This is within the manufacturers specified 5 to 10%
overcharge which indicates that the battery should see a much
improved cycle-life compared to test case #1. Until this test
is concluded it is difficult to say how long the battery will
cycle. The test data here only indicates that this battery is
being recharged within the recommended limits.

Figure 6. Test
Case #1, Corner Point, PV Cycle-Life Test

Figure 7. Test
Case #15, Center Point, PV Cycle-Life Test
Sandia is now working with Morningstar and Digital Solar Technologies
to test lower cost, improved performance, and higher reliability
charge controllers such as the SunSaver PWM charge controller
and the MPR-9400 microprocessor based PV charge controller. Some
examples of this work are identified below.
The development of this charge controller was partially funded
by Sandia as part of DOE's Photovoltaic BOS Program. The SunSaver
has been in field tests for over six months. The SunSaver has
demonstrated exceptional performance and reliability for a small
(<10 amps) low cost PV charge controller. It increases charge
acceptance in VRLA batteries which should improve VRLA battery
cycle-life. The increased charge acceptance is due to the PWM
charge algorithm. Previous work11 has indicated that
improved charge acceptance is possible "
by discharging
prior to charging or during the charging process". Figure
8 is an example of the PWM charging algorithm in the SunSaver.
The charge and discharge current pulses may be responsible for
the improved charge acceptance seen when used with VRLA batteries.
Field tests have shown that the SunSaver does provide VRLA batteries
with a much higher overcharge or charge acceptance.
Figure 9 is an example of how the PV Battery Cycle-Life Test can
be used to evaluate battery charge acceptance. In this test the
Morningstar SunSaver was placed in series with the Firing Circuits
automated battery tester to make a direct comparison between DC
constant voltage charging and PWM charging using the same VRLA
battery and test program for both charge algorithms. This battery
survived over 200 cycles of the PV Battery Cycle-Life Test before
it "permanently" lost over 20% of its capacity (99 to
73 Ah). The battery capacity could not be recovered with constant
voltage charging using recommended charging procedures. SunSaver
PV Battery Cycle-Life Test results now indicate that much of the
battery capacity has been recovered. This is illustrated by the
deficit charge cycle which removed 74 Ah at 11.46 volts. Previous
capacity tests on this battery resulted in about 10 Ah of battery
capacity between 11.5 and 10.5 volts. This indicates that an
increase in battery capacity of about 11 Ah has occurred from
the SunSaver PWM PV charge controller.

Figure 8.
SunSaver Pulse Width Modulated
Charging Showing Charge and Discharge Current Spikes
The test results in Figure 9 also indicate that the Morningstar
SunSaver is providing the GNB 12-5000X AGM VRLA battery with 2
to 8% more overcharge compared to the constant voltage charge
algorithm. In addition to the increased overcharge, the PWM charge
controller is charging at 14.0 volts instead of 14.1 volts due
to a voltage drop from the internal electrical resistance in the
battery tester. The SunSaver is also charging the battery at
about 25C compared to the constant voltage data at about 27C.

Figure 9. PV Battery Cycle-Life Test Comparing Constant Voltage Charging vs. The SunSaver Pulse Width Modulated Charging Using A GNB 12-5000X VRLA Battery
Both of these factors will reduce the overcharge for the PWM charger.
In addition to the laboratory tests, field test results have
shown that the SunSaver provides a much higher overcharge (>25%).
The above test results certainly indicate that the PWM charger
will charge the battery more efficiently with a lower voltage.
Tests are continuing to evaluate the effect PWM and overcharge
will have on battery cycle-life.
A new amp-hour (Ah) counting PV charge control algorithm developed
in a cooperative effort with Digital Solar Technologies
and implemented in their MPR-9400 microprocessor based
PV charge controller is presently under test at Sandia. Previous
Sandia analysis of PV hybrid power systems indicated that traditional
voltage regulated charge control was not the most effectively
way to charge batteries for hybrid power systems with multiple
power sources and complex loads. Battery management in complex
hybrid systems is difficult because of daily and seasonal load
or DOD changes and fluctuations in solar resource. The new Digital
Solar Technologies MPR-9400 Ah counting charge control algorithm
and automatic battery equalization function have already demonstrated
in preliminary testing that flooded deep-cycle batteries can be
charged in a more effective way in hybrid power systems. Work
is presently underway to demonstrate this new charge algorithm
for the GNB VRLA battery technology.
The new Ah counting charge control algorithm requires the user to input several parameters into the MPR-9400. These parameters include:
Figure 10 shows the first test results for a GNB 12-5000X AGM VRLA battery bank. The Ah counting charge control disables the high voltage disconnect (HVD) 1 and 2 when the specified overcharge in Ah is reached (BatAH). The charge control algorithm requires the input of: 1) the battery capacity (BATAHINIT), 2) the preset maximum overcharge (%OVER), 3) a battery Ah adjustment for regulation voltage (%ADD), and 4) the cycle reset voltage (AHVRESET). The data in Figure 10 is calculated using the Campbell data logger and it indicates that the MPR-9400 is able to recharge the VRLA battery to within 1.5 Ah every day (253 to 254.5 Ah). This resulted in a battery overcharge based on depth of discharge of 7.9 to 12%, which is within the battery manufacturer's recommended values.

Figure 10.
Ah Counting Charge Control on
GNB 12-5000X VRLA Batteries. Battery Capacity Measured Using
MPR-9400 Charge Control Algorithm. Battery Temperature is 13
to 15C.
When the Ah counting charge control algorithm has completed its
initial performance testing, it will be a significant advancement
in PV hybrid charge control strategy. VRLA battery charge control
will be greatly improved by providing the maximum available charge
without under- or over-charging the batteries in variable resource
and load periods. This will extend cycle-life by reducing dry-out
and maximizing state of charge.
The Sandia PV battery testing program has already made significant steps toward its goal of improved PV battery cycle-life and lower life-cycle costs. This work has produced:
Work is now continuing to complete the cycle-life testing at Sandia
and FSEC and to confirm field performance improvements using the
new PV charge controllers. The PV battery and charge controller
survey, battery test results, and charge controller test results
will be distributed to the PV industry to help facilitate improved
system design, more reliable PV systems, and lower life-cycle
costs.
Without the work and support of Garth Corey from Sandia's Battery
Analysis & Evaluation Department, the battery survey would
not have been done. This work was a significant and much appreciated
addition to the PV battery testing program. Also the work of
Ramu Swamy and Jim Dunlop at FSEC has been essential in conducting
the PV Battery Life-Cycle Test.
1. Woodworth, J.R., Harrington, S.R., Dunlop, J.D.,
et al, "Evaluation of the Batteries and Charge Controllers
in Small Stand-alone Photovoltaic Systems", First World Conference
on Photovoltaic Energy Conversion, Hawaii, Dec. 1994.
2. Harrington S. R., Hund T. D., "Photovoltaic
Lighting System Performance," 25th IEEE Photovoltaic
Specialists Conference, Washington, May 1996. Pp. 1307-1400.
3. Hammond R. L., Turpin J. F., Corey G., Hund T.,
and Harrington S. R., "Photovoltaic Battery & Charge
Controller Market & Applications Survey - An Evaluation Of
The Photovoltaic System Market For 1995," Sandia Contractor
Report # SAND96-xxxx, Dec. 1996.
4. Whitehead M. L., "Failure Mechanisms In
VRLA Batteries," Proc. of 8th Battery Conference
and Exhibition, Solihull, UK, May 1994, pp. 2.1.1 - 2.1.10.
5. Strong S., The Solar Electric House, "Voltage
Regulators, Battery Chargers, Storage Batteries," Solar Design
Associates, Inc., (508) 456-6855.
6. University of Cape Town Energy for Development
Research Centre, Remote Area Power Supply (RAPS) Design Manual,
ISBN:0 7992 1435 3, Ph. (021) 650-3230, Sept. 1992.
7. Battery Council International, Battery Technical
Manual 2nd Edition, 401 North Michigan Av. Chicago,
Illinois 60611, (312) 644-6610.
8. Dunlop J., and Swamy R., "Evaluation of
Batteries and Charge Controllers In Small Stand-Alone PV Systems,"
Florida Solar Energy Center, Contractor Reports, Nov. 1996.
9. S.R. Harrington, and T. D. Hund, "Rating
Batteries for Initial Capacity, Charging Parameters and Cycle
Life in the Photovoltaic Application", PCIM , Sept.,
1995
10. Box G.E.P., Hunter W.G., and Hunter J.S., Statistics
For Experimenters, Wiley, NY, 1978.
11. Joseph A. Mas, "The Charging Process," Proc. 2nd Int. Electric Vehicle Symposium, Electric Vehicle Council, 1971, pp. 228-246.